I'm Being Charged More Than the Estimate.  What Can I Do?

Original Estimates May Be Imposed As Final Pricing Unless a Notice of Change Was Provided.

Understanding When Pricing May Change Within An Estimated Price Contract Depends Upon the Contract

Estimated Price Contract Document When a supplier of services, such as a contractor, mechanic, mover, among others, provides an estimated price, the law requires that the eventual invoice will somewhat resemble the initial estimate. Unless unforeseeable circumstances arise, and a notice of change to the original estimate was provided, the customer is typically 'right' in a dispute over a substantial difference between the final price and the originally estimated price. Without properly letting the client know that the final price will be considerably higher than the estimate, the supplier may get stuck to charging the initially estimated price.

The Law
I'm Being Charged More Than the Estimate.  What Can I Do?

Generally, it appears that only business-to-consumer relations have pricing estimates protected and governed by statute.  In Ontario, the Consumer Protection Act, 2002, S.O. 2002, Chapter 30, Schedule A, provides that estimated pricing within a consumer agreement shall be within ten (10%) percent of the final pricing unless amendments were approved by the consumer and the supplier.  Specifically, the Consumer Protection Act, 2002 states:


Estimates

10 (1) If a consumer agreement includes an estimate, the supplier shall not charge the consumer an amount that exceeds the estimate by more than 10 per cent.

Performance of consumer agreement

(2) If a supplier charges an amount that exceeds the estimate by more than 10 per cent, the consumer may require that the supplier provide the goods or services at the estimated price.

Subsequent agreement

(3) Nothing in this section prevents a consumer and a supplier from agreeing to amend the estimate or price in a consumer agreement, if the consumer requires additional or different goods or services.

For business-to-business matters, where a statute law addressing the issue of estimates fails to exist, the common law case of Go Island Hopper Helicopters Ltd. v. Rotech Industries Inc., 1996 CanLII 2448, appears to address the issue whereas it was said:


68  Further, in the event that there was only an estimate, I would apply the law enunciated by Wright J. in Kozik v. Melnick, [1991] O.J. No. 1259 (Ont. C.J.) which concerned a quantum meruit claim arising from the refurbishment of an aircraft.  The court held at p. 5:

In approaching this matter I proceed on the assumption:

(1)  That a man is entitled to fair compensation for effort expended.

(2)  That an "estimate" is not a contract.

(3)  That while an estimate may not constitute an enforceable agreement, the conduct of the claimant, viz.:  (a) his failure to keep the customer advised of the necessity to increase the fees beyond the estimate, and (b) the failure to inform the customer that other charges would be charged separately may dictate that the original estimate be adhered to.  See: Thomson, Rogers and Croyden Furniture Systems Inc. (1982), 16 A.C.W.S. (2d) 196.

(4)  That where circumstances change the customer is entitled to be warned of the change.  Re: Solicitor (May 10th, 1967).

(5)  That where an honest misunderstanding arises over the extent of the work to be done for the amount stipulated the Court will lean against the party who might have taken steps to have avoided the misunderstanding.

Re: Phelan, O'Brien, Shannon, Lawer and Kozaroff (1981), 8 A.C.W.S. (2d) 494.

69  If this is an estimate case as opposed to a contract case, in my view the plaintiff was entitled to be warned of any change in the defendant's estimate.

Summary Comment

Unless the customer makes changes to the scope of project or object purchase, a supplier to a consumer will quite likely be held to a final price that is within ten (10%) percent of the estimated price.  For a customer in a business-to-business matter, the protection is informal and appears imposed merely by the common law without statutory mandate; however the Go Island Hopper case suggests that without a warning of pricing change from the supplier, the supplier may be held to, or close to, the original estimated price.  With this said, there may still be room to argue that pricing should be based on a fair value for the work done, or what is known in law as quantum meruit, so to avoid an unjust enrichment.

Need Help?Let's Get Started Today

ATTENTION: Do not send any confidential information through this web form.  Use this web form only to make an introduction.

Send a Message Directly to Anderson Aylwin Begg & Co.

ATTENTION: Confidential details about your case must not be sent through this website.  Use of this website does not establish a legal-representative/client relationship.  Do not include confidential details about your case by email or phone.  Use this website only for an introduction with Anderson Aylwin Begg & Co.. 
Privacy Policy & Cookies | Terms of Use Your IP Address is: 34.230.84.106
Anderson Aylwin Begg & Co.

58 Rossland Road W, Suite 210
Oshawa, Ontario,
L1G 2V5

P: (905) 686-8080
F: (416) 391-6071
E: reception@aablegalservices.com

Hours of Business:

09:00AM - 05:00PM
09:00AM - 05:00PM
09:00AM - 05:00PM
09:00AM - 05:00PM
09:00AM - 05:00PM
Monday:
Tuesday:
Wednesday:
Thursday:
Friday:

By appointment only.  Call for details.
Messages may be left anytime.







Sign Up